Oslo
Norway's data centre market powered by near-zero-carbon hydroelectric energy. Cold climate enables free cooling year-round, attracting hyperscale investment.
80MW
Total Capacity
12
Active Facilities
5.5%
Vacancy Rate
$0.055/kWh
Power Cost
180MW
Pipeline
3/10
Regulatory Risk
$160K/acre
Land Cost
14mo
Permit Timeline
Capacity Growth Trend
+180 MW pipelineMarket Highlights
- 98% renewable energy - nearly zero-carbon grid from hydropower
- Microsoft $6.2B investment in Narvik data centre campus
- Cold climate enables year-round free cooling
98%
Renewable Energy
15 MW
Annual Absorption
Market Risk Factors
High VacancyVacancy rate of 5.5% may indicate oversupply risk
Key Providers
Green MountainDigiPlexBulk